Wind farm costs – Guide to an offshore wind farm (2024)

LCOE reduction can come from reduced costs, increased energy production or changes in financing and lifetime of the project. Reduced cost can be from process or technology changes during the manufacturing, installation or operations phase. Increased energy production may be as a result of technology or by reducing lost energy via better operational processes. Reducing project risk is the main way to affect financing cost.

As shown in the chart, LCOE across Europe varies between projects (blue dots) but overall are continuing to reduce significantly over time. The LCOE has been back-calculated based on assumptions of full-life revenue & transmission costs, where applicable, as well as the auction price). The band takes into account range in site conditions and support mechanisms / local requirements that impact LCOE.

Some of the key drivers of cost are:

  • Site conditions. Typically, projects in deeper water require more expensive foundations and have increased installation cost. Easier ground conditions such as dense sand with low gradients on hom*ogeneous, stiff clay containing few (if any) boulders offer cost benefits as a range of piling solutions can be used and there is high confidence of long-term foundation stability. Other conditions can add significantly to cost by driving a need for alternative designs and installation methods, such as larger diameter monopiles or drilling into rock or through boulders.

Average and storm wind and wave conditions, tidal ranges and tidal flows also impact LCOE. Higher mean wind speeds increase cost, but have a net benefit for LCOE due to increased energy production. In some markets (for example in Asia), typhoon winds drive design changes that add cost. Tidal ranges add to cost due to having to keep a minimum clearance from sea level to blade tip at all times. Tides and waves make it harder to access turbines, especially for unplanned service activities in bad weather, adding cost and reducing energy production.

Likewise, projects further from shore take longer to access, which adds cost and increases downtime, hence reducing energy production. At about 60km, it may be most cost effective to use a service operation vessel (SOV) spending weeks at sea, rather than crew transfer vessels (CTVs) travelling to and from port daily. Projects further from shore typically also have longer grid connections, adding to transmission CAPEX and OPEX.

  • Over time, there has been a move by governments from providing an agreed fixed-value market mechanism to support offshore wind to auctions where project developers bid a price for electricity they will generate. This change drives competition at project level which is passed down through the supply chain. Also, as the industry matures, what used to be highly differentiated areas of supply become commodities, driving further competition.

In some areas, such as turbines, the market is not big enough to have more than a handful of suppliers competing globally. This limits competition. In other areas, such as cables and foundations, transport costs are low enough to enable a geographically diverse supply base to bid for supply. In areas such as provision of port services, distance to the wind farm is key, which localises competition.

Vessel charter prices are a good example of the impact of pan-sector competition. Whether considering large floating installation vessels or common tugs, cyclic variations in regional wind and oil and gas activity can have a significant effect of price. Large turbine and foundation jack-up vessels are typically purpose-built for wind, so price volatility depends much more on the pipeline of offshore wind projects.

  • Supply chain evolution. Over time, the supply chain has matured and larger players have taken on wider scopes and more risk. Wider scope within one supplier has enabled more cross-disciplinary collaboration to reduce cost. Also, larger volumes have facilitated investment in design, manufacturing and installation tooling suited to higher-volume process repetition. Large offshore wind farms may use 100 sets of identical (or similar) components, quite different from the more common practice in oil and gas of constructing one-offs.
  • Technology development. To date, the biggest driver over time of cost of energy reduction has been the development of new technology. The most visible sign of this has been the increase in turbine rating, increasing from 2MW turbines 20 years ago to 10MW turbines for projects being given the go-ahead today. The rate of growth has been extraordinary and has enabled offshore wind projects in some parts of Europe to compete on cost of energy with onshore projects in other parts of Europe.

Larger turbines help drive down the per MW cost of foundations, installation and operation, whilst reaching higher into the wind field, so increasing energy production per MW installed. Larger turbines drive a need for technology development at a component level, as offshore wind turbines use the largest castings, bearings, generators and composite structures in series manufacture in any industry.

Industry incorporation of digital, autonomous, artificial intelligence and other applicable technologies is also enabling significant cost reduction, especially through improved wind farm operation and control.

Typical costs have been provided based on a project with the following parameters, typical of an upcoming UK offshore wind project.

ParameterData
Wind farm rating (MW)1000
Wind turbine rating (MW)10
Water depth at site (m)30
Annual mean wind speed at 100m height (m/s)10
Distance to shore, grid, port (km)60
Date of financial investment decision to proceed (FID)2019
First operation date2022

Detailed, bottom-up assessment of this typical project gives the following inputs to the LCOE equation:

  • Total CAPEX = £2,370,000/MW (with spend spread realistically over years leading up to first energy production)
  • Annual average OPEX = £76,000/MW
  • Lifetime = 27 years
  • WACC = 6.0%
  • Net annual average energy production = 4,471MWh/year/MW

As discussed above there can be quite a range in prices of any element, due to specific timing or local issues, exchange rates, competition and contracting conditions. Prices for large components include delivery to nearest port to supplier and warranty costs. Developer costs (including internal project- and construction management, insurance, typically spent contingency and overheads) are included in the highest-level boxes but are not itemised.

A more detailed breakdown of typical costs is presented in the table below. Note that figures presented are each rounded, hence totals may not equate to the sum of the sub-terms. As discussed above, there can be a large variation in costs between projects, so values stated should only be seen as indicative.

CategoryRounded cost (£/MW)
Development and project management120,000
Development and consenting services50,000
Environmental impact assessments8,000
Other (includes developer staff hours and other subcontract work)42,000
Environmental surveys4,000
Benthic environmental surveys450
Fish and shellfish surveys400
Ornithological environmental surveys1,000
Marine mammal environmental surveys1,000
Onshore environmental surveys550
Human impact studies350
Resource and metocean assessment4,000
Structure3,000
Sensors650
Maintenance300
Geological and hydrological surveys4,000
Geophysical surveys700
Geotechnical surveys2,500
Hydrographic surveys800
Engineering and consultancy4,000
Other (includes lost projects that incur development expenditure)54,000
Turbine1,000,000
Nacelle400,000
Bedplate20,000
Main bearing20,000
Main shaft20,000
Gearbox70,000
Generator100,000
Power take-off70,000
Control system25,000
Yaw system17,000
Yaw bearing7,000
Nacelle auxiliary systems7,000
Nacelle cover10,000
Small engineering components25,000
Structural fasteners7,000
Rotor190,000
Blades130,000
Hub casting15,000
Blade bearings20,000
Pitch system10,000
Spinner2,000
Rotor auxiliary systems4,000
Fabricated steel components8,000
Structural fasteners7,000
Tower70,000
Steel60,000
Tower internals7,000
Other (includes assembly, wind turbine supplier aspects of installation and commissioning, profit and warranty)340,000
Balance of plant600,000
Cables170,000
Export cable130,000
Array cable35,000
Cable protection2,000
Turbine foundation280,000
Transition piece100,000
Corrosion protection20,000
Scour protection10,000
Offshore substation120,000
Electrical system45,000
Facilities20,000
Structure60,000
Onshore substation30,000
Buildings, access and security8,000
Other (includes electrical equipment and systems)22,000
Operations base3,000
Installation and commissioning650,000
Foundation installation100,000
Offshore substation installation35,000
Onshore substation construction25,000
Onshore export cable installation5,000
Offshore cable installation220,000
Cable burial20,000
Cable pull-in7,500
Electrical testing and termination6,500
Other (includes cable-laying vessel, survey works, route clearance, cable protection systems186,000
Turbine installation50,000
Offshore logistics3,500
Sea-based support2,500
Marine coordination850
Weather forecasting and metocean data300
Other (insurance, contingency (spent) and construction project management)212,000
Operation, maintenance and service (per annum)75,000
Operations25,000
Training500
Onshore logistics450
Offshore logistics1,600
Health and safety inspections400
Other (insurance, environmental studies and compensation payments)22,000
Maintenance and service50,000
Turbine maintenance and service33,000
Balance of plant maintenance and service18,000
Decommissioning330,000
Turbine decommissioning45,000
Foundation decommissioning75,000
Cable decommissioning140,000
Substation decommissioning65,000
Wind farm costs – Guide to an offshore wind farm (2024)

FAQs

How much does an offshore wind farm cost? ›

Wind turbine installation costs are estimated to range between USD 0.5 million and USD 1 million, while the cost of foundation installation ranges from USD 1 million and USD 1.5 million per unit.

What is the cost of offshore wind energy? ›

In 2021, the cost of installed offshore wind energy worldwide averaged 2,858 U.S. dollars per kilowatt, a year-over-year decrease of over 12 percent. This figure has been on a mostly continual downward trend since 2011, when it reached the peak of the decade at more than 5,500 dollars per kilowatt.

How much does an offshore wind farm cost UK? ›

The average value of the actual capex costs reported for onshore wind farms completed in 2016-19 was £1.61 million per MW, for offshore wind it was £4.49 million per MW (including transmission) or £3.99 million if the very expensive Hywind project is excluded.

How much does it cost to install a wind farm? ›

A 1000-MW wind farm costs $1,750 million to install all the turbines (500 turbines x $3.5M per turbine). For a lifetime of 15 years, the costs is $116 million per year (1,750/15).

How much does a 10 MW offshore wind turbine cost? ›

"Thus, for this analysis, we estimate that the cost of a 10 MW turbine is $8 million, while a 12 MW and a 14 MW turbine would cost approximately $10.1 million and $12.3 million, respectively.

Are offshore wind farms cost-effective? ›

Offshore wind is not cost-effective, and the forecasts of rapidly declining costs through increasing economies of scale are unrealistic.

Top Articles
Latest Posts
Article information

Author: Dong Thiel

Last Updated:

Views: 5718

Rating: 4.9 / 5 (59 voted)

Reviews: 82% of readers found this page helpful

Author information

Name: Dong Thiel

Birthday: 2001-07-14

Address: 2865 Kasha Unions, West Corrinne, AK 05708-1071

Phone: +3512198379449

Job: Design Planner

Hobby: Graffiti, Foreign language learning, Gambling, Metalworking, Rowing, Sculling, Sewing

Introduction: My name is Dong Thiel, I am a brainy, happy, tasty, lively, splendid, talented, cooperative person who loves writing and wants to share my knowledge and understanding with you.